Ghana Gas Company rehabilitates two bridges

  • SOURCE: | qwesa2big
  • The Ghana Gas Company Limited has rehabilitated two bailey bridges in the Ellembele District at a total cost of about GHC570,000.

    Dr. George Adjah Sipa Yankey, Chief Executive Officer of the company, said on Monday.

    He was briefing the press when he led Mr. Paul Evans Aidoo, Western Regional Minister, and Mr. Emmanuel Armah Kofi Buah, Deputy Minister of Energy, to inspect the bridges at Essiama and Eikwe.

    Dr. Yankey said the bridge at Essiama was rehabilitated at a cost of GHC300, 000, whilst the Eikwe bridge cost GHC270,000.

    He said the company decided to fund the rehabilitation of the bridges when feasibility studies revealed they were structurally weak and could not carry pipelines and heavy duty machinery and equipment for the Gas Processing Plant at Atuabo.

    The rehabilitation works were undertaken by the Ghana Highways Authority, which also took part in the feasibility studies, Dr. Yankey said.

    He said, “The rehabilitation was to extend the bridges and strengthen them to facilitate the transportation of pipelines and heavy machinery in order not to hamper the gas processing plant project”.

    Mr. Aidoo said the rehabilitation works had to be carried out for the Gas Processing Plant Project to go on as planned.

    GNA

    Leave a reply

    About Us
    Reporting Oil and Gas project was launched on 4th June 2009 at Takoradi, Western Region, Ghana by Penplusbytes (www.penplusbytes.org) with the vision of providing a one stop online information and knowledge about Ghana’s oil and gas sector read more
    Twitter Activity Stream
     

    Partners We are proud to be associated with:

    Skip to toolbar